Governing norm · exact excerpt
“may take into account the probable consequences of interim measures for all interests likely to be harmed, as well as the public interest”
Council Directive 89/665/EEC on public procurement review procedures · Directive 89/665/EEC, Article 2(5); reproduced in the judgment
Open official provision ↗
The Court interpreted Article 2(3) to (5) together with Article 47 of the Charter, focusing on effective interim judicial protection and an actual weighing of the competing interests.
Court holding · exact excerpt
“without first hearing the unsuccessful tenderer that brought that action and without being able to weigh up all the interests at stake”
Judgment, paragraph 53 and operative part
Official EUR-Lex judgment — Joined Cases C-266/25 and C-267/25, I-Sete ↗
Legal issue
Whether national legislation may require a court to provisionally lift the automatic suspensive effect of a challenge to a public-contract award, in order to avoid the loss of European funding, without first hearing the unsuccessful tenderer or weighing all interests on the merits.
What the court held
Article 2(3) to (5) of Directive 89/665, read in the light of Article 47 of the Charter, precludes national legislation that requires provisional lifting of an automatic suspension for the objective of avoiding loss of EU funding where the tenderer is not first heard and the court cannot weigh all interests on the merits.
Reasoning that matters
- Paragraphs 28–31The Remedies Directive requires effective and rapid review and protects the pre-contractual period through interim measures and, for award challenges, an automatic suspension until the review body has acted.
- Paragraphs 33–39Lifting the suspension limits the right to an effective remedy and must satisfy the Charter requirements applicable to limitations on that right.
- Paragraphs 46–48The court hearing the interim application must itself be able to weigh the interests at stake; national legislation cannot replace that judicial assessment with an abstract predetermined balance.
- Paragraph 53 and operative partAvoiding loss of European funding does not permit a rule that requires provisional lifting without hearing the tenderer and without a substantive balancing of interests.
Procedural status / outcome
The Court interpreted the Remedies Directive and Article 47 of the Charter as precluding the Portuguese mechanism described by the referring court. The national court must decide the joined disputes consistently with that interpretation.
Cross-border angle
The judgment concerns the EU-wide minimum standard for effective procurement remedies and is particularly relevant to projects financed or co-financed by European funds, where timing pressures may conflict with pre-contractual judicial protection.
What counsel should take from it
- Procurement legislation cannot make the risk of losing EU financing an automatic trump card against interim judicial protection.
- A court asked to lift suspensive effect must retain the ability to hear the affected tenderer and conduct a case-specific weighing of interests.
- Contracting authorities and beneficiaries of EU-funded projects should factor review-risk and standstill timing into project planning instead of relying on automatic procedural acceleration.
- The judgment concerns the judicial-remedies stage; it does not determine the substantive legality of the underlying procurement awards.
Temporal and procedural limits
The judgment was delivered on 17 September 2026 in joined cases concerning Portuguese public contracts for floating photovoltaic facilities and the risk of losing project financing.
Later-development check. Official EUR-Lex and CURIA materials checked through 22 September 2026 disclosed no later CJEU judicial development altering the judgment.
Editorial note. Exact source passages are separated from editorial analysis. The analysis must be read with the complete judgment and applicable law.