Governing norm · exact excerpt
“This Regulation shall apply, in situations involving a conflict of laws, to contractual obligations in civil and commercial matters.”
Regulation (EC) No 593/2008 (Rome I) and Regulation (EC) No 864/2007 (Rome II) · Rome I Article 1(1), first sentence, reproduced at judgment paragraph 19; related provisions reproduced at paragraphs 16 and 22
Open official provision ↗
Verified relevant provisions reproduced in the official judgment. Rome II Article 8(1): “The law applicable to a non-contractual obligation arising from an infringement of an intellectual property right shall be the law of the country for which protection is claimed.” Rome I Article 11(1): “A contract concluded between persons who, or whose agents, are in the same country at the time of its conclusion is formally valid if it satisfies the formal requirements of the law which governs it in substance under this Regulation or of the law of the country where it is concluded.” Article 11(2): “A contract concluded between persons who, or whose agents, are in different countries at the time of its conclusion is formally valid if it satisfies the formal requirements of the law which governs it in substance under this Regulation, or of the law of either of the countries where either of the parties or their agent is present at the time of conclusion, or of the law of the country where either of the parties had his habitual residence at that time.” These alternatives must be assessed on the facts; the Court did not select Polish or German law.
Court holding · exact excerpt
“the issue of the formal validity of the assignment contract […] is a contractual matter”
Paragraph 56 and operative part; reasoning at paragraphs 45–55
Official InfoCuria judgment and case file — C-176/25, Steizer (Judgment → Open sheet) ↗
Legal issue
Which conflict-of-laws regime governs the formal validity of an author's assignment of exclusive rights to use photographs when an alleged third-party infringer challenges the assignee's title?
What the court held
The rules of Rome I determine the law applicable to formal validity of the author-to-assignee contract. A third party's reliance on a defect of form does not turn that issue into a non-contractual or proprietary-rights question. This conclusion leaves the territorial law governing copyright protection and the Rome II rule governing infringement intact.
Reasoning that matters
- Paragraphs 27–34A German online seller relied on photographs commissioned from a Polish photographer under oral agreements. An alleged infringer challenged the formal validity of the assignment, arguing for Polish law and a writing requirement. Those were competing submissions, not findings by the Court that the assignment was invalid.
- Paragraphs 42–46The infringement claim is non-contractual, but formal validity of the assignment is independent of liability for infringement. Requirements of form concern the parties' expression of their voluntarily assumed obligation.
- Paragraph 47Using the contractual conflict-of-laws regime provides predictability where exclusive rights are enforceable in several Member States and infringements may attract several territorial laws.
- Paragraphs 48–53Formal validity is distinguished from copyright's intrinsic characteristics, protected subject matter and authorship. That validity question remains contractual even where the applicable form requirement is found in domestic copyright legislation and affects the assignee's title.
- Paragraphs 54–56The territorial protection of copyright remains unaffected. If the national court finds the assignment formally valid or the claimant otherwise holds the relevant exclusive rights in Germany, the infringement must still be assessed under the law identified by Rome II Article 8(1).
Procedural status / outcome
The Court answered the reference by classifying formal validity of the assignment as contractual under Rome I. It did not decide the national-law outcome, the validity of the particular oral agreements or the infringement claim; those issues remain for the referring court.
Cross-border angle
The dispute directly concerns a German trader, a Polish photographer, orally agreed rights and online sales. It matters when rights acquired across borders are enforced in EU courts against third parties and the chain of title is challenged.
For U.S. Counsel
U.S. businesses commissioning or acquiring content for EU use should distinguish contract-form analysis from the territorial law governing infringement. The decision is an EU conflicts ruling; it does not resolve U.S. copyright formalities or determine the validity of a particular acquisition.
Open U.S. Counsel overview →What counsel should take from it
- Analyse the chain of title and the alleged infringement as separate conflict-of-laws questions.
- For an assignment of exclusive rights of use, check Rome I's formal-validity alternatives instead of assuming that the law protecting copyright also governs the contract's form.
- Document the parties, conclusion locations, contractual law and evidence of the grant when commissioning photographs or other protected works across borders.
- Do not read this decision as deciding every proprietary effect of an assignment or harmonising national writing requirements.
Temporal and procedural limits
The judgment was delivered on 24 September 2026 and is added to this service on 2 October as a verified backfill. The oral transactions at issue dated from 2014 to 2018. The text is marked provisional, and Steizer is a fictitious case name.
Later-development check. The live official InfoCuria case file checked on 2 October 2026 lists the judgment of 24 September 2026, the earlier Advocate General Opinion of 23 April 2026 and closed preliminary-ruling proceedings. No subsequent document altering this result was listed in that case file.
Editorial note. Exact source passages are separated from editorial analysis. The analysis must be read with the complete judgment and applicable law.